The Clark County Building Department publishes a first-review goal of twenty-one days for a Custom Single Family Residence. Revisions add ten days each. Phased projects can take up to forty-two days. City of Las Vegas and City of Henderson have their own timelines and submission requirements. Lot location determines which jurisdiction governs your build, and the design-build firm should know each jurisdiction’s process before submission.